首頁 \ 關(guān)于遠(yuǎn)東
|
| 首頁 關(guān)于遠(yuǎn)東 產(chǎn)品目錄 銷售網(wǎng)絡(luò) 生產(chǎn)設(shè)備 技術(shù)支持 公司資質(zhì) 聯(lián)系我們
螺桿泵的安裝說明Pump installation instructions
| | | |
① 泵的吸入, 排出管路的管徑不得小于泵的進(jìn)、出口口徑, 管路力求簡短, 減少不必要的損失(如彎頭等)。泵的安裝高度, 長度應(yīng)保證泵工作時(shí)不超過允許的吸上真空高度。(1) of the pump suction and discharge line of the pipe diameter shall not be less than the inlet and outlet of pump diameter, pipe to short, reduce unnecessary losses (such as elbow, etc.).Pump installation height, length should guarantee the pump working shall not exceed the permitted on vacuum suction height.
② 管路應(yīng)有管架, 泵不允許承受管路的負(fù)荷。安裝前對(duì)吸入、排出管路要清理干凈, 去掉鐵銹等臟物, 特別是焊接管路的焊渣必須徹底清除, 以免進(jìn)入泵后咬死。(2) the line pipe rack, pump are not allowed to bear load of pipeline.Before installation on the suction and discharge line to clean, remove rust and dirt, especially welding pipe welding slag must be thoroughly cleared, to avoid killed after entering the pump.
③吸入管路應(yīng)設(shè)裝過濾器, 其濾網(wǎng)為40-80目, 有效過濾器面積大于吸入口徑的8-15倍。(3) suction pipe should be installed filters, the mesh is 40-80 mesh, the effective filter area is greater than the suction diameter of 8-15 times.
④螺桿泵進(jìn)、出口處應(yīng)連接真空表(或真空壓力表)和壓力表, 以便觀察泵工作狀態(tài)。(4) the pump inlet and outlet should be connected vacuum gauge or vacuum pressure gauge and pressure gauge, in order to observe the pump working status.
⑤如有兩臺(tái)以上的泵并聯(lián)在同一管路上, 在泵出口處必須安裝逆止閥, 保證泵的正常工作。5. If you have more than two pumps in parallel in the same way, must be installed at pump outlet check valve, to ensure the normal operation of the pump.
⑥安裝泵的位置應(yīng)寬暢, 方便檢修。將機(jī)組放在地腳螺栓的基礎(chǔ)上, 找正后擰緊地腳螺栓。6. The location of the installation of pump should be enlarged, convenient maintenance.Unit on the basis of the anchor bolt, after looking for is tighten the anchor bolts.
⑦在接好管路及確定電機(jī)轉(zhuǎn)向后接聯(lián)軸器, 聯(lián)軸器外圓同心度允差為0.1毫米, 兩聯(lián)軸器端面間隙允差為2毫米。
7 after good pick up line and to determine the motor coupling, coupling cylindrical concentricity tolerance is 0.1 mm, two coupling end clearance tolerance of 2 mm.
⑧ 機(jī)組運(yùn)轉(zhuǎn)3-4小時(shí)后作最后檢查, 如無不良現(xiàn)象, 則認(rèn)為安裝合格。Sets operate after 3-4 hours today for final inspection, if there is no negative phenomenon, is considered qualified installation.
⑨ 保溫泵在泵進(jìn)口方向的背面分別接有管閥1、2。泵啟動(dòng)前閥1和閥2應(yīng)完全打開,通入保溫用的汽(液)后,并達(dá)到規(guī)定的保溫溫度時(shí)方能開啟泵機(jī)組。若工作正常不需供保溫的汽(液)時(shí),可關(guān)閉閥1,注意排氣閥2不能關(guān)閉。
⑩與泵聯(lián)接的進(jìn)出口管道,法蘭一定要清潔,嚴(yán)禁雜質(zhì)、焊渣殘留管內(nèi)。Pet-name ruby heat pump on the back of the pump inlet direction with the pipe valves 1, 2, respectively.Before starting the pump valve 1 and 2 should be fully open, after going into the insulation with steam (liquid), and meet the heat preservation temperature, in order to open the pump unit.If work does not need for insulation of steam (liquid), close the valve 1, pay attention to the exhaust valve 2 cannot be closed.Attending to the import and export of pump connection pipes, flanges must be clean, impurity, welding slag residual tube shall be strictly prohibited.
技術(shù)支持:
螺桿泵技術(shù)支持一
螺桿泵技術(shù)支持二
螺桿泵技術(shù)支持三
螺桿泵技術(shù)支持四
|